August 27, 2026
On July 2, 2026, an email went out to residents across western Prince William County. "The Arc of Justice bent hard in our favor," the Coalition to Protect Prince William County wrote in an email reported by WTOP, announcing that QTS Data Centers had just withdrawn its final legal challenge at the Virginia Supreme Court. That ended a three-year fight over the Prince William Digital Gateway, a proposed 1,760-acre corridor of up to 37 data centers along Pageland Lane in rural Gainesville. It was the second time opponents had celebrated. The first came in March, when the Court of Appeals sided with them and residents gathered at Giuseppe's Ristorante Italiano to mark the win. The Oak Valley Homeowners Association, whose members paid an extra $1,000 apiece in HOA dues to raise roughly $250,000 for legal fees, treated both moments as vindication.
For buyers considering a home near that corridor, two matters remain relevant: property tax assessments on the parcels involved and the land-use designation, which remains in place because the court rulings addressed the specific rezoning, not the Comprehensive Plan Amendment.
For buyers comparing homes in western Gainesville, the litigation is closed, while related zoning and assessment processes remain in motion.
The Digital Gateway traces back to 2021, when Gainesville landowner Mary Ann Ghadban began organizing neighbors along Pageland Lane to bundle more than 200 properties for sale to data center developers QTS and Compass Datacenters. The Prince William Board of County Supervisors approved the rezonings in December 2023 after a hearing that ran into the next morning.
The legal fight that followed moved fast once it got moving:
The case has closed, and county actions on zoning maps and assessments continue.
The Court of Appeals decision addressed the 2023 rezonings specifically. It did not touch the 2022 Comprehensive Plan Amendment that first designated the Pageland Lane corridor as a future technology zone, because that separate legal challenge to the CPA failed on different grounds back in 2025. The county's own planning office spells out the distinction plainly on its Digital Gateway project page: the rezonings are void and the properties revert to their prior zoning, but the Comprehensive Plan Amendment stands, because the Court of Appeals upheld that action separately.
| What changed in July 2026 | What stayed the same |
|---|---|
| The 2023 rezonings are void; parcels revert to their pre-2023 zoning (Agricultural/Estate) | The 2022 Comprehensive Plan Amendment designating the corridor for technology use remains in effect |
| QTS and Compass no longer have entitlements to build on the land | A future developer could still file a new rezoning application on the same land |
| The specific 2023 approval process is dead | Any new application would need to restart the full process: planning staff review, Planning Commission hearing, Board of Supervisors vote |
The designation remains in place even though the specific approval process ended. A comprehensive plan designation isn't a permit, but it's the document county staff and supervisors point to when a rezoning application comes back through the pipeline. The county's own site notes that "any future effort to rezone the property would need to go through the normal rezoning application process," which is true, but it also means the door was never welded shut. It was just closed on this particular attempt.
Here's the part that will actually show up in a title search or a tax record if you're looking at a home near Pageland Lane this year. When the county rezoned those parcels for data center use in 2023, its finance office reassessed them using an unusual formula. Bristow Beat reported that land was valued at its "highest and best use," which along the corridor meant roughly $1.5 million per acre in commercial value. But because the rezoning was still tied up in litigation, the assessor applied a series of discounts. One documented formula, from county records, worked out to $1,500,000 multiplied by 0.50, then 0.65, then 0.90, landing at $438,750 per acre for parcels under contract to sell.
Some individual results were more dramatic. Mary Ann Ghadban's own residence, the property at the center of the assemblage, saw its 2023 assessed value of $1,829,200 drop 98 percent to $31,200 in 2024. Her home structure alone was assessed at a token $100, because the county's stated assumption was that any structure on these parcels would be razed for construction. Nearly a dozen other Pageland Lane properties saw similar cuts.
That formula only made sense as long as the rezoning was moving toward completion. It no longer is. The county's own July 29, 2026 implementation order states that once the zoning maps are corrected, "Real Estate Assessments will then work to reassess all the individual properties and update the tax bills," including any penalties and interest that apply.
Most Gainesville buyers looking at established communities like Piedmont, Dominion Valley, or Virginia Oaks were never geographically close enough to this corridor for any of this to matter. The Digital Gateway footprint sat specifically along Pageland Lane, between Sudley Road and Route 29, bordering the Manassas National Battlefield Park.
But if a home you're considering sits near that boundary, three things are worth confirming before you write an offer:
Could a data center still get built on Pageland Lane someday? Legally, yes. The Comprehensive Plan Amendment designating the corridor for technology use was upheld and remains in place. A developer could file a new rezoning application, which would have to go through the county's standard planning process from scratch, including new public hearings. Given how the current Board of Supervisors voted in April 2026 to stop defending the project, a near-term revival looks unlikely, but it isn't legally foreclosed.
Where can I check whether a specific address was part of the Digital Gateway footprint? The Prince William County Planning Office maintains project documentation on its Digital Gateway page, and the county's Real Estate Assessments Office can confirm a parcel's zoning and assessment history directly.
Gainesville's housing market has plenty to recommend it that has nothing to do with any of this. If you're looking at a property near the Pageland Lane corridor, the county's assessment process is still underway. If you want a second set of eyes on a specific address before you make an offer, Krissy Cruse has been tracking this market long enough to tell you what's actually on the books, not just what made the news.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.
Stay up to date on the latest real estate trends.
Thanksgiving Hosting Guide & Prep Timeline | Krissy Cruse
I am committed to guiding you every step of the way—whether you're buying a home, selling a property, or securing a mortgage. Whatever your needs, I've got you covered.